Details Of Nerul-Belapur-Uran Railway Line

In this post I am sharing the details of the Nerul-Uran Railway Line.

Sources-CIDCO
Salient Features
Length27 km. approx..
Approved Cost By Railway BoardRs.1412.17 crores ( 2009 price level)
Date of startJune / July - 1997
Number of stations10
Names: Seawoods,Sagarsangam, Targhar, Bamandongari Kharkopar,Gavan,Ranjanpada, Nhavasheva,Dronagiri & Uran)
Road over bridges15 Nos.
Track under bridge1 No
Major bridgesImportant bridge of 751 m span across Panvel creek completed, 4 major bridges, one viaduct.
Number of rakes11 Nos./td>
Platforms: 270 m platforms for four B.G. tracks to cater 12 car EMU rakes with double discharge facility.
Tripartite agreement between CIDCO, Govt. of Maharashtra and Railways and commercial development agreement between CIDCO and Railways signed on 29.07.2011






















The Construction of Railway line is in full swing.The over water bridge work is completed. The deadlines For 1st Phase i.e till Kharkopar Station is December, 2017.2nd phase deadline (till Uran) is December,2018. Layouting of tracks is also started along the bamandongri station and kharkopar station in Sector-19,20,23 and 15,16,17 In Ulwe.